Project Timeline
From award to completion — tracking every milestone.
Actual: 11 Oct 2026
Select any milestone for its dates.
Steps from the project's recorded dates; the detailed programme of works appears once the Ministry publishes it.
Before & After
Real change. Real impact.

Awka · Awka South Oct 2026 vs Oct 2026
Earliest and latest published photos; viewpoints may differ.
Latest Field Updates
Photos and progress from the project site.
Site photos14 Oct 2026
Public Observations & Feedback
View AllNo public observations yet. Only consented, moderated and redacted summaries appear here. Confidential cases stay private.
Report an observationFull timeline
-
Contract award
Completed · planned 17 Sept 2025 · actual 17 Sept 2025
-
Works commence
Completed · planned 17 Sept 2025 · actual 17 Sept 2025
-
Works 70% complete
In Progress · actual 11 Oct 2026
-
Practical completion
Upcoming · planned 19 Mar 2026
-
Defects period ends
Upcoming
Why the status reads “Under construction”
- Measured progress (70%) is 30 points behind the time used (100%).
- The planned completion date has passed.
Map & Segments
Get directionsThe road line and its segments appear once the Ministry digitises the alignment.
Updates
Photos & Videos
5 photos, newest first
Citizen Feedback
No public observations yet. Only consented, moderated and redacted summaries appear here. Confidential cases stay private.
Report an observationDocuments
No public document has been attached to this project yet. Award notices and scope summaries appear here when the Ministry publishes them.
Project factsheet