The Supply and Installation of Mechanical (LOT B) Appurtnances in the Sid Permanent Building

Road works in Awka South LGA, Anambra Central, delivered by Project Guarranty LTD, supervised by the Ministry of Works.

Latest site photo, 14 Oct 2026
Project codeANSG/MOW/PRJ/2026/023
StatusUnder construction
Measured progress70% (measured 11 Oct 2026)
LocationAwka, Awka South LGA, Anambra Central
ContractorProject Guarranty LTD
Supervising ministryMinistry of Works, Highways
Contract sumNot published
Commencement17 Sept 2025
Planned completion19 Mar 2026

Timeline

Contract awardCompleted · planned 17 Sept 2025 · actual 17 Sept 2025
Works commenceCompleted · planned 17 Sept 2025 · actual 17 Sept 2025
Works 70% completeIn Progress · actual 11 Oct 2026
Practical completionUpcoming · planned 19 Mar 2026
Defects period endsUpcoming

Source: Anambra State Ministry of Works project records, as published on Road Tracker. https://roads.anambrastate.gov.ng/p/the-supply-and-installation-of-mechanical-lot-b-appurtnances-55c1d705