Construction of Ugwuaku Ibughugbu Osu Umuchu Road, Aguata LGA, Anambra State
Road works in Aguata LGA, Anambra South, delivered by Benejaf, supervised by the Ministry of Works.
- UmuchuAguata LGA, Anambra State
- State RoadPD/S Department
Project Timeline
From award to completion — tracking every milestone.
Actual: 11 Oct 2026
Select any milestone for its dates.
Steps from the project's recorded dates; the detailed programme of works appears once the Ministry publishes it.
Before & After
Real change. Real impact.
A before-and-after comparison appears once photos from two different dates are published for this project.
Latest Field Updates
Photos and progress from the project site.
Photos appear here as engineers file their daily site reports.
Public Observations & Feedback
View AllNo public observations yet. Only consented, moderated and redacted summaries appear here. Confidential cases stay private.
Report an observationFull timeline
-
Contract award
Completed · planned 21 Aug 2025 · actual 21 Aug 2025
-
Works commence
Completed · planned 21 Aug 2025 · actual 21 Aug 2025
-
Works 75% complete
In Progress · actual 11 Oct 2026
-
Practical completion
Upcoming · planned 22 Apr 2026
-
Defects period ends
Upcoming
Why the status reads “Under construction”
- Measured progress (75%) is 25 points behind the time used (100%).
- The planned completion date has passed.
- No photo update has been published yet.
Map & Segments
Get directionsThe road line and its segments appear once the Ministry digitises the alignment.
Updates
No update has been published yet.
Photos & Videos
0 photos, newest first
No photo has been published yet.
Citizen Feedback
No public observations yet. Only consented, moderated and redacted summaries appear here. Confidential cases stay private.
Report an observationDocuments
No public document has been attached to this project yet. Award notices and scope summaries appear here when the Ministry publishes them.