Road Tracker, Anambra State

Project factsheet · generated 16 Oct 2026

Construction of Ugwuaku Ibughugbu Osu Umuchu Road, Aguata LGA, Anambra State

Road works in Aguata LGA, Anambra South, delivered by Benejaf, supervised by the Ministry of Works.

Project codeANSG/MOW/PRJ/2026/038
StatusUnder construction
Measured progress75% (measured 11 Oct 2026)
LocationUmuchu, Aguata LGA, Anambra South
ContractorBenejaf
Supervising ministryMinistry of Works, PD/S
Contract sumNot published
Commencement21 Aug 2025
Planned completion22 Apr 2026

Timeline

Contract awardCompleted · planned 21 Aug 2025 · actual 21 Aug 2025
Works commenceCompleted · planned 21 Aug 2025 · actual 21 Aug 2025
Works 75% completeIn Progress · actual 11 Oct 2026
Practical completionUpcoming · planned 22 Apr 2026
Defects period endsUpcoming

Source: Anambra State Ministry of Works project records, as published on Road Tracker. https://roads.anambrastate.gov.ng/p/construction-of-ugwuaku-ibughugbu-osu-umuchu-road-aguata-lga-9d1a5cc7

Back to the project