Road infrastructure project

Construction of the Road Connecting St. Augustine Community Primary School-Rest Assured Hotel-Commuinty High School-Umunze Ultra Modern Market to the Umunze-Umuchu Bypass Road

Road works in Orumba South LGA, Anambra South, delivered by Saidi NIG. LTD, supervised by the Ministry of Works.

  • Rest Assured / Umunze AxisOrumba South LGA, Anambra State
  • State RoadMES Department
Not publishedProject Value
—Total Length
1 LGAOrumba South
Not yet estimatedPeople Benefiting

Project Timeline

From award to completion — tracking every milestone.

View Full Timeline
Works 90% complete · In Progress
Actual: 11 Oct 2026
Select any milestone for its dates.

Steps from the project's recorded dates; the detailed programme of works appears once the Ministry publishes it.

Before & After

Real change. Real impact.

A before-and-after comparison appears once photos from two different dates are published for this project.

Latest Field Updates

Photos and progress from the project site.

View All Media

Site photos13 Oct 2026

Public Observations & Feedback

View All

No public observations yet. Only consented, moderated and redacted summaries appear here. Confidential cases stay private.

Report an observation

Full timeline

  1. Contract award

    Completed · planned 1 Jun 2025 · actual 1 Jun 2025

  2. Works commence

    Completed · planned 30 Jun 2025 · actual 30 Jun 2025

  3. Works 90% complete

    In Progress · actual 11 Oct 2026

  4. Practical completion

    Upcoming · planned 1 Mar 2026

  5. Defects period ends

    Upcoming

Why the status reads “Under construction”

  • Measured progress (90%) is in line with the time used (100%).
  • The planned completion date has passed.

Map & Segments

Get directions

The road line and its segments appear once the Ministry digitises the alignment.

Updates

Photos & Videos

2 photos, newest first

Site photo, 13 Oct 2026
13 Oct 2026
Site photo, 13 Oct 2026
13 Oct 2026

Citizen Feedback

No public observations yet. Only consented, moderated and redacted summaries appear here. Confidential cases stay private.

Report an observation

Documents

No public document has been attached to this project yet. Award notices and scope summaries appear here when the Ministry publishes them.

Project factsheet

Share this project

Seal of Anambra State

Infrastructure
People
ProgressMinistry of Works · Anambra State

See every project. Say what you see. See what happens next.

Explore every road project