Project factsheet · generated 16 Oct 2026
Construction of the Road Connecting St. Augustine Community Primary School-Rest Assured Hotel-Commuinty High School-Umunze Ultra Modern Market to the Umunze-Umuchu Bypass Road
Road works in Orumba South LGA, Anambra South, delivered by Saidi NIG. LTD, supervised by the Ministry of Works.
| Project code | ANSG/MOW/PRJ/2026/014 |
|---|---|
| Status | Under construction |
| Measured progress | 90% (measured 11 Oct 2026) |
| Location | Rest Assured / Umunze Axis, Orumba South LGA, Anambra South |
| Contractor | Saidi NIG. LTD |
| Supervising ministry | Ministry of Works, MES |
| Contract sum | Not published |
| Commencement | 30 Jun 2025 |
| Planned completion | 1 Mar 2026 |
Timeline
| Contract award | Completed · planned 1 Jun 2025 · actual 1 Jun 2025 |
|---|---|
| Works commence | Completed · planned 30 Jun 2025 · actual 30 Jun 2025 |
| Works 90% complete | In Progress · actual 11 Oct 2026 |
| Practical completion | Upcoming · planned 1 Mar 2026 |
| Defects period ends | Upcoming |
Source: Anambra State Ministry of Works project records, as published on Road Tracker. https://roads.anambrastate.gov.ng/p/construction-of-the-road-connecting-st-augustine-community-primary-de712aaf