Road infrastructure project
Construction of Increte Finishing on the Median and Triangular Islands Along the 5.2km Willie Obiano Boulevard (Chinua Achebe Int’L Airport Road) Umueri
Road works in Anambra East LGA, Anambra North, delivered by Navigator Sign LTD, supervised by the Ministry of Works.
- UmueriAnambra East LGA, Anambra State
- State RoadHighways Department
Project Timeline
From award to completion — tracking every milestone.
Actual: 13 Oct 2026
Select any milestone for its dates.
Steps from the project's recorded dates; the detailed programme of works appears once the Ministry publishes it.
Before & After
Real change. Real impact.

Umueri · Anambra East Oct 2026 vs Oct 2026
Earliest and latest published photos; viewpoints may differ.
Latest Field Updates
Photos and progress from the project site.
Site photos14 Oct 2026
Public Observations & Feedback
View AllNo public observations yet. Only consented, moderated and redacted summaries appear here. Confidential cases stay private.
Report an observationFull timeline
-
Contract award
Completed · planned 17 Sept 2026 · actual 17 Sept 2026
-
Works commence
Completed · planned 17 Sept 2026 · actual 17 Sept 2026
-
Works 30% complete
In Progress · actual 13 Oct 2026
-
Practical completion
Upcoming · planned 26 Nov 2026
-
Defects period ends
Upcoming
Why the status reads “Under construction”
- Measured progress (30%) is in line with the time used (42%).
Map & Segments
Get directionsThe road line and its segments appear once the Ministry digitises the alignment.
Updates
Photos & Videos
4 photos, newest first
Citizen Feedback
No public observations yet. Only consented, moderated and redacted summaries appear here. Confidential cases stay private.
Report an observationDocuments
No public document has been attached to this project yet. Award notices and scope summaries appear here when the Ministry publishes them.
Project factsheet