Road infrastructure project
Construction and Dualization of the Aerotropolis 10.725km Road from Airport Junction to Isiagu (LOT 2 of the Access Road to the Anambra Aerotropolis) with 2 Nr Bridges
Road works in Orumba North LGA, Anambra South, delivered by IDC Construction NIG. LTD, supervised by the Ministry of Works.
- Orumba North/Isiagu(Awka South)Orumba North LGA, Anambra State
- State RoadPD/S Department
Project Timeline
From award to completion — tracking every milestone.
Actual: 11 Oct 2026
Select any milestone for its dates.
Steps from the project's recorded dates; the detailed programme of works appears once the Ministry publishes it.
Before & After
Real change. Real impact.
A before-and-after comparison appears once photos from two different dates are published for this project.
Latest Field Updates
Photos and progress from the project site.
Site photos14 Oct 2026
Public Observations & Feedback
View AllNo public observations yet. Only consented, moderated and redacted summaries appear here. Confidential cases stay private.
Report an observationFull timeline
-
Contract award
Completed · planned 24 Sept 2026 · actual 24 Sept 2026
-
Works commence
Completed · planned 24 Sept 2026 · actual 24 Sept 2026
-
Works 0% complete
In Progress · actual 11 Oct 2026
-
Practical completion
Upcoming · planned 24 Sept 2027
-
Defects period ends
Upcoming
Why the status reads “Under construction”
- Measured progress (0%) is in line with the time used (6%).
Map & Segments
Get directionsThe road line and its segments appear once the Ministry digitises the alignment.
Updates
Photos & Videos
5 photos, newest first
Citizen Feedback
No public observations yet. Only consented, moderated and redacted summaries appear here. Confidential cases stay private.
Report an observationDocuments
No public document has been attached to this project yet. Award notices and scope summaries appear here when the Ministry publishes them.
Project factsheet