Project factsheet · generated 16 Oct 2026
The Supply and Installation of Electrical Appurtenances in the Sid Permanent Building
Road works in Awka South LGA, Anambra Central, delivered by Project Guarranty LTD, supervised by the Ministry of Works.
| Project code | ANSG/MOW/PRJ/2026/022 |
|---|---|
| Status | Under construction |
| Measured progress | 70% (measured 13 Oct 2026) |
| Location | Awka, Awka South LGA, Anambra Central |
| Contractor | Project Guarranty LTD |
| Supervising ministry | Ministry of Works, Highways |
| Contract sum | Not published |
| Commencement | 20 Nov 2025 |
| Planned completion | 22 May 2026 |
Timeline
| Contract award | Completed · planned 20 Nov 2025 · actual 20 Nov 2025 |
|---|---|
| Works commence | Completed · planned 20 Nov 2025 · actual 20 Nov 2025 |
| Works 70% complete | In Progress · actual 13 Oct 2026 |
| Practical completion | Upcoming · planned 22 May 2026 |
| Defects period ends | Upcoming |
Source: Anambra State Ministry of Works project records, as published on Road Tracker. https://roads.anambrastate.gov.ng/p/the-supply-and-installation-of-electrical-appurtenances-in-the-1a836ac6