The Production and Installation of 500 Pieces of Flourescent" Solution Is Here" Concrete Signage for the Branding of All Landmark Infrastructures Across the State (Phase 2)

Road works in Awka South LGA, Anambra Central, delivered by Conifer Konstuktion NIG. LTD, supervised by the Ministry of Works.

Project codeANSG/MOW/PRJ/2026/045
StatusUnder construction
Measured progress61.7% (measured 11 Oct 2026)
LocationAwka, Awka South LGA, Anambra Central
ContractorConifer Konstuktion NIG. LTD
Supervising ministryMinistry of Works, PD/S
Contract sumNot published
Commencement26 May 2025
Planned completion26 Jul 2025

Timeline

Contract awardCompleted · planned 26 May 2025 · actual 26 May 2025
Works commenceCompleted · planned 26 May 2025 · actual 26 May 2025
Works 62% completeIn Progress · actual 11 Oct 2026
Practical completionUpcoming · planned 26 Jul 2025
Defects period endsUpcoming