Project factsheet · generated 16 Oct 2026
The Production and Installation of 500 Pieces of Flourescent" Solution Is Here" Concrete Signage for the Branding of All Landmark Infrastructures Across the State (Phase 2)
Road works in Awka South LGA, Anambra Central, delivered by Conifer Konstuktion NIG. LTD, supervised by the Ministry of Works.
| Project code | ANSG/MOW/PRJ/2026/045 |
|---|---|
| Status | Under construction |
| Measured progress | 61.7% (measured 11 Oct 2026) |
| Location | Awka, Awka South LGA, Anambra Central |
| Contractor | Conifer Konstuktion NIG. LTD |
| Supervising ministry | Ministry of Works, PD/S |
| Contract sum | Not published |
| Commencement | 26 May 2025 |
| Planned completion | 26 Jul 2025 |
Timeline
| Contract award | Completed · planned 26 May 2025 · actual 26 May 2025 |
|---|---|
| Works commence | Completed · planned 26 May 2025 · actual 26 May 2025 |
| Works 62% complete | In Progress · actual 11 Oct 2026 |
| Practical completion | Upcoming · planned 26 Jul 2025 |
| Defects period ends | Upcoming |
Source: Anambra State Ministry of Works project records, as published on Road Tracker. https://roads.anambrastate.gov.ng/p/the-production-and-installation-of-500-pieces-of-flourescent-181637bb