Project factsheet · generated 16 Oct 2026
Reclamation/Rechannelization and Remediation of Gully Erosion Site at Umugama - Ire Villiage Abba Njikoka LGA
Road works in Njikoka LGA, Anambra Central, delivered by P & K INT'L LTD, supervised by the Ministry of Works.
| Project code | ANSG/MOW/PRJ/2026/019 |
|---|---|
| Status | Under construction |
| Measured progress | 100% (measured 13 Oct 2026) |
| Location | Abba Njikoka LGA, Njikoka LGA, Anambra Central |
| Contractor | P & K INT'L LTD |
| Supervising ministry | Ministry of Works, Highways |
| Contract sum | Not published |
| Commencement | 16 Jan 2025 |
| Planned completion | 17 Jun 2025 |
Timeline
| Contract award | Completed · planned 16 Jan 2025 · actual 16 Jan 2025 |
|---|---|
| Works commence | Completed · planned 16 Jan 2025 · actual 16 Jan 2025 |
| Works 100% complete | In Progress · actual 13 Oct 2026 |
| Practical completion | Upcoming · planned 17 Jun 2025 |
| Defects period ends | Upcoming |
Source: Anambra State Ministry of Works project records, as published on Road Tracker. https://roads.anambrastate.gov.ng/p/reclamation-rechannelization-and-remediation-of-gully-erosion-site-at-f7661ebd