Construction Of Ukwuorji Awka Umunechi Villiage – Ifite Nibo – Isiagu Junction with a 0.60KM Spur to Ziks Avenue and 1.5km Spur to Oye Nwuchichi Road, Anambra State (Distance=5.025km)

Road works in Awka South LGA, Anambra Central, delivered by J. Quarison Int’l LTD, supervised by the Ministry of Works.

Project codeANSG/MOW/PRJ/2026/026
StatusUnder construction
Measured progress85% (measured 11 Oct 2026)
LocationAwka, Nibo & Isiagu, Awka South LGA, Anambra Central
ContractorJ. Quarison Int’l LTD
Supervising ministryMinistry of Works, Highways
Contract sumNot published
Commencement11 Aug 2023
Planned completion10 Jan 2024

Timeline

Contract awardCompleted · planned 11 Aug 2023 · actual 11 Aug 2023
Works commenceCompleted · planned 11 Aug 2023 · actual 11 Aug 2023
Works 85% completeIn Progress · actual 11 Oct 2026
Practical completionUpcoming · planned 10 Jan 2024
Defects period endsUpcoming

Source: Anambra State Ministry of Works project records, as published on Road Tracker. https://roads.anambrastate.gov.ng/p/construction-of-ukwuorji-awka-umunechi-villiage-ifite-nibo-isiagu-5ee1d45e