Project factsheet · generated 16 Oct 2026
Construction Of Ukwuorji Awka Umunechi Villiage – Ifite Nibo – Isiagu Junction with a 0.60KM Spur to Ziks Avenue and 1.5km Spur to Oye Nwuchichi Road, Anambra State (Distance=5.025km)
Road works in Awka South LGA, Anambra Central, delivered by J. Quarison Int’l LTD, supervised by the Ministry of Works.
| Project code | ANSG/MOW/PRJ/2026/026 |
|---|---|
| Status | Under construction |
| Measured progress | 85% (measured 11 Oct 2026) |
| Location | Awka, Nibo & Isiagu, Awka South LGA, Anambra Central |
| Contractor | J. Quarison Int’l LTD |
| Supervising ministry | Ministry of Works, Highways |
| Contract sum | Not published |
| Commencement | 11 Aug 2023 |
| Planned completion | 10 Jan 2024 |
Timeline
| Contract award | Completed · planned 11 Aug 2023 · actual 11 Aug 2023 |
|---|---|
| Works commence | Completed · planned 11 Aug 2023 · actual 11 Aug 2023 |
| Works 85% complete | In Progress · actual 11 Oct 2026 |
| Practical completion | Upcoming · planned 10 Jan 2024 |
| Defects period ends | Upcoming |
Source: Anambra State Ministry of Works project records, as published on Road Tracker. https://roads.anambrastate.gov.ng/p/construction-of-ukwuorji-awka-umunechi-villiage-ifite-nibo-isiagu-5ee1d45e