Road Tracker, Anambra State

Project factsheet · generated 16 Oct 2026

Construction of Uga-Amesi-Otikpo Road

Road works in Aguata LGA, Anambra South, delivered by Joviani Engineering LTD, supervised by the Ministry of Works.

Project codeANSG/MOW/PRJ/2026/013
StatusUnder construction
Measured progress82% (measured 11 Oct 2026)
LocationUga, Aguata LGA, Anambra South
ContractorJoviani Engineering LTD
Supervising ministryMinistry of Works, MES
Contract sumNot published
Commencement30 Dec 2024
Planned completion30 Jun 2025

Timeline

Contract awardCompleted · planned 1 Dec 2024 · actual 1 Dec 2024
Works commenceCompleted · planned 30 Dec 2024 · actual 30 Dec 2024
Works 82% completeIn Progress · actual 11 Oct 2026
Practical completionUpcoming · planned 30 Jun 2025
Defects period endsUpcoming

Source: Anambra State Ministry of Works project records, as published on Road Tracker. https://roads.anambrastate.gov.ng/p/construction-of-uga-amesi-otikpo-road-571a3482

Back to the project