Road Tracker, Anambra State

Project factsheet · generated 16 Oct 2026

Construction of the main building in the permanent site of the solution innovation district

Road works in Awka South LGA, Anambra Central, delivered by Dutum Company LTD, supervised by the Ministry of Works.

Latest site photo, 14 Oct 2026
Project codeANSG/MOW/PRJ/2026/010
StatusUnder construction
Measured progress90% (measured 11 Oct 2026)
LocationSolution Innovation District / Old Government House Awka, Awka South LGA, Anambra Central
ContractorDutum Company LTD
Supervising ministryMinistry of Works, MES
Contract sumNot published
Commencement30 Apr 2024
Planned completion1 May 2025

Timeline

Contract awardCompleted · planned 1 Apr 2024 · actual 1 Apr 2024
Works commenceCompleted · planned 30 Apr 2024 · actual 30 Apr 2024
Works 90% completeIn Progress · actual 11 Oct 2026
Practical completionUpcoming · planned 1 May 2025
Defects period endsUpcoming

Source: Anambra State Ministry of Works project records, as published on Road Tracker. https://roads.anambrastate.gov.ng/p/construction-of-the-main-building-in-the-permanent-site-64230e53