Project factsheet · generated 16 Oct 2026
Construction of the main building in the permanent site of the solution innovation district
Road works in Awka South LGA, Anambra Central, delivered by Dutum Company LTD, supervised by the Ministry of Works.
| Project code | ANSG/MOW/PRJ/2026/010 |
|---|---|
| Status | Under construction |
| Measured progress | 90% (measured 11 Oct 2026) |
| Location | Solution Innovation District / Old Government House Awka, Awka South LGA, Anambra Central |
| Contractor | Dutum Company LTD |
| Supervising ministry | Ministry of Works, MES |
| Contract sum | Not published |
| Commencement | 30 Apr 2024 |
| Planned completion | 1 May 2025 |
Timeline
| Contract award | Completed · planned 1 Apr 2024 · actual 1 Apr 2024 |
|---|---|
| Works commence | Completed · planned 30 Apr 2024 · actual 30 Apr 2024 |
| Works 90% complete | In Progress · actual 11 Oct 2026 |
| Practical completion | Upcoming · planned 1 May 2025 |
| Defects period ends | Upcoming |
Source: Anambra State Ministry of Works project records, as published on Road Tracker. https://roads.anambrastate.gov.ng/p/construction-of-the-main-building-in-the-permanent-site-64230e53