Construction of Paved Areas (Kerbs Interlocking) LOT 4 Within the Government (Light House), Awka

Road works in Awka South LGA, Anambra Central, delivered by Prodigy Gardens, supervised by the Ministry of Works.

Project codeANSG/MOW/PRJ/2026/025
StatusUnder construction
Measured progress90% (measured 11 Oct 2026)
LocationAwka, Awka South LGA, Anambra Central
ContractorProdigy Gardens
Supervising ministryMinistry of Works, Highways
Contract sumNot published
Commencement14 Jun 2024
Planned completion6 Sept 2024

Timeline

Contract awardCompleted · planned 14 Jun 2024 · actual 14 Jun 2024
Works commenceCompleted · planned 14 Jun 2024 · actual 14 Jun 2024
Works 90% completeIn Progress · actual 11 Oct 2026
Practical completionUpcoming · planned 6 Sept 2024
Defects period endsUpcoming

Source: Anambra State Ministry of Works project records, as published on Road Tracker. https://roads.anambrastate.gov.ng/p/construction-of-paved-areas-kerbs-interlocking-lot-4-within-e7fe19c5