Project codeANSG/MOW/PRJ/2026/024
StatusUnder construction
Measured progress92.5% (measured 11 Oct 2026)
LocationOko, Ogboji, Orumba North LGA, Anambra South
ContractorCossel Const. CO. NIG LTD
Supervising ministryMinistry of Works, Highways
Contract sumNot published
Commencement5 Sept 2024
Planned completion5 Nov 2025

Timeline

Contract awardCompleted · planned 5 Sept 2024 · actual 5 Sept 2024
Works commenceCompleted · planned 5 Sept 2024 · actual 5 Sept 2024
Works 93% completeIn Progress · actual 11 Oct 2026
Practical completionUpcoming · planned 5 Nov 2025
Defects period endsUpcoming