Project factsheet · generated 16 Oct 2026
Construction of Ihiala - Umudara - Ndiezike Road, Ihiala, LGA
Road works in Ihiala LGA, Anambra South, delivered by Rojel NIG. LTD, supervised by the Ministry of Works.
| Project code | ANSG/MOW/PRJ/2026/011 |
|---|---|
| Status | Under construction |
| Measured progress | 35% (measured 11 Oct 2026) |
| Location | Ihiala, Ihiala LGA, Anambra South |
| Contractor | Rojel NIG. LTD |
| Supervising ministry | Ministry of Works, MES |
| Contract sum | Not published |
| Commencement | 7 May 2024 |
| Planned completion | 5 May 2025 |
Timeline
| Contract award | Completed · planned 1 Apr 2024 · actual 1 Apr 2024 |
|---|---|
| Works commence | Completed · planned 7 May 2024 · actual 7 May 2024 |
| Works 35% complete | In Progress · actual 11 Oct 2026 |
| Practical completion | Upcoming · planned 5 May 2025 |
| Defects period ends | Upcoming |
Source: Anambra State Ministry of Works project records, as published on Road Tracker. https://roads.anambrastate.gov.ng/p/construction-of-ihiala-umudara-ndiezike-road-ihiala-lga-d97982ec