Project factsheet · generated 16 Oct 2026

Construction of Ihiala - Umudara - Ndiezike Road, Ihiala, LGA

Road works in Ihiala LGA, Anambra South, delivered by Rojel NIG. LTD, supervised by the Ministry of Works.

Project codeANSG/MOW/PRJ/2026/011
StatusUnder construction
Measured progress35% (measured 11 Oct 2026)
LocationIhiala, Ihiala LGA, Anambra South
ContractorRojel NIG. LTD
Supervising ministryMinistry of Works, MES
Contract sumNot published
Commencement7 May 2024
Planned completion5 May 2025

Timeline

Contract awardCompleted · planned 1 Apr 2024 · actual 1 Apr 2024
Works commenceCompleted · planned 7 May 2024 · actual 7 May 2024
Works 35% completeIn Progress · actual 11 Oct 2026
Practical completionUpcoming · planned 5 May 2025
Defects period endsUpcoming

Source: Anambra State Ministry of Works project records, as published on Road Tracker. https://roads.anambrastate.gov.ng/p/construction-of-ihiala-umudara-ndiezike-road-ihiala-lga-d97982ec

Back to the project