Road Tracker, Anambra State

Project factsheet · generated 16 Oct 2026

Construction of Additional Storm Water Discharge Drainage Channels Along the Newly Constructed Abba Junction - Nawgu - Isuanaocha - Achalla - Ikem Nando Road

Road works in Awka North LGA, Anambra Central, delivered by MP - Infrastructure, supervised by the Ministry of Works.

Project codeANSG/MOW/PRJ/2026/033
StatusUnder construction
Measured progress0% (measured 11 Oct 2026)
LocationNawgu/Isuanaocha, Awka North LGA, Anambra Central
ContractorMP - Infrastructure
Supervising ministryMinistry of Works, PD/S
Contract sumNot published
Commencement24 Sept 2026
Planned completion19 Nov 2026

Timeline

Contract awardCompleted · planned 24 Sept 2026 · actual 24 Sept 2026
Works commenceCompleted · planned 24 Sept 2026 · actual 24 Sept 2026
Works 0% completeIn Progress · actual 11 Oct 2026
Practical completionUpcoming · planned 19 Nov 2026
Defects period endsUpcoming