Project factsheet · generated 16 Oct 2026
Construction of Additional External Works within the Solution Innovation District (SID) Complex
Road works in Awka South LGA, Anambra Central, delivered by Bigxent Technologies, supervised by the Ministry of Works.
| Project code | ANSG/MOW/PRJ/2026/008 |
|---|---|
| Status | Under construction |
| Measured progress | 30% (measured 14 Oct 2026) |
| Location | Awka, Awka South LGA, Anambra Central |
| Contractor | Bigxent Technologies |
| Supervising ministry | Ministry of Works, MES |
| Contract sum | Not published |
| Commencement | 17 Sept 2026 |
| Planned completion | 17 Dec 2026 |
Timeline
| Contract award | Completed · planned 17 Sept 2026 · actual 17 Sept 2026 |
|---|---|
| Works commence | Completed · planned 17 Sept 2026 · actual 17 Sept 2026 |
| Works 30% complete | In Progress · actual 14 Oct 2026 |
| Practical completion | Upcoming · planned 17 Dec 2026 |
| Defects period ends | Upcoming |
Source: Anambra State Ministry of Works project records, as published on Road Tracker. https://roads.anambrastate.gov.ng/p/construction-of-additional-external-works-within-the-solution-innovation-aaf5b304