Project codeANSG/MOW/PRJ/2026/041
StatusUnder construction
Measured progress70% (measured 11 Oct 2026)
LocationUmunya, Oyi LGA, Anambra North
ContractorSenatorch
Supervising ministryMinistry of Works, PD/S
Contract sumNot published
Commencement17 Oct 2025
Planned completion17 Oct 2026

Timeline

Contract awardCompleted · planned 17 Oct 2025 · actual 17 Oct 2025
Works commenceCompleted · planned 17 Oct 2025 · actual 17 Oct 2025
Works 70% completeIn Progress · actual 11 Oct 2026
Practical completionUpcoming · planned 17 Oct 2026
Defects period endsUpcoming