Project factsheet · generated 16 Oct 2026
Construction of Access Road to University on the Niger, Umunya
Road works in Oyi LGA, Anambra North, delivered by Senatorch, supervised by the Ministry of Works.
| Project code | ANSG/MOW/PRJ/2026/041 |
|---|---|
| Status | Under construction |
| Measured progress | 70% (measured 11 Oct 2026) |
| Location | Umunya, Oyi LGA, Anambra North |
| Contractor | Senatorch |
| Supervising ministry | Ministry of Works, PD/S |
| Contract sum | Not published |
| Commencement | 17 Oct 2025 |
| Planned completion | 17 Oct 2026 |
Timeline
| Contract award | Completed · planned 17 Oct 2025 · actual 17 Oct 2025 |
|---|---|
| Works commence | Completed · planned 17 Oct 2025 · actual 17 Oct 2025 |
| Works 70% complete | In Progress · actual 11 Oct 2026 |
| Practical completion | Upcoming · planned 17 Oct 2026 |
| Defects period ends | Upcoming |
Source: Anambra State Ministry of Works project records, as published on Road Tracker. https://roads.anambrastate.gov.ng/p/construction-of-access-road-to-university-on-the-niger-865350af