Project factsheet · generated 16 Oct 2026
Construction of Access Road Leading to Seraphic Home Foundation Umueri
Road works in Anambra East LGA, Anambra North, delivered by Korea Mirae Construction COY NIG. LTD, supervised by the Ministry of Works.
| Project code | ANSG/MOW/PRJ/2026/044 |
|---|---|
| Status | Under construction |
| Measured progress | 48.4% (measured 11 Oct 2026) |
| Location | Umueri, Anambra East LGA, Anambra North |
| Contractor | Korea Mirae Construction COY NIG. LTD |
| Supervising ministry | Ministry of Works, PD/S |
| Contract sum | Not published |
| Commencement | 5 Jul 2026 |
| Planned completion | 25 Oct 2026 |
Timeline
| Contract award | Completed · planned 5 Jul 2026 · actual 5 Jul 2026 |
|---|---|
| Works commence | Completed · planned 5 Jul 2026 · actual 5 Jul 2026 |
| Works 48% complete | In Progress · actual 11 Oct 2026 |
| Practical completion | Upcoming · planned 25 Oct 2026 |
| Defects period ends | Upcoming |
Source: Anambra State Ministry of Works project records, as published on Road Tracker. https://roads.anambrastate.gov.ng/p/construction-of-access-road-leading-to-seraphic-home-foundation-3e082908