Construction of Abba Junction - Nawgu - Isuaniocha - Achalla - Ikem Nando Road

Road works in Awka North LGA, Anambra Central, delivered by MP - Infrastructure, supervised by the Ministry of Works.

Project codeANSG/MOW/PRJ/2026/037
StatusUnder construction
Measured progress95% (measured 11 Oct 2026)
LocationNawgu/Isuanaocha, Awka North LGA, Anambra Central
ContractorMP - Infrastructure
Supervising ministryMinistry of Works, PD/S
Contract sumNot published
Commencement1 Jun 2024
Planned completion1 Dec 2025

Timeline

Contract awardCompleted · planned 1 Jun 2024 · actual 1 Jun 2024
Works commenceCompleted · planned 1 Jun 2024 · actual 1 Jun 2024
Works 95% completeIn Progress · actual 11 Oct 2026
Practical completionUpcoming · planned 1 Dec 2025
Defects period endsUpcoming

Source: Anambra State Ministry of Works project records, as published on Road Tracker. https://roads.anambrastate.gov.ng/p/construction-of-abba-junction-nawgu-isuaniocha-achalla-ikem-nando-06bd2350