Road Tracker, Anambra State

Project factsheet · generated 16 Oct 2026

Construction of 16.51km (LOT2) Nnewi to Ozubulu to Okija with a 370m Spur and 3 Span Bridge Across the Ulasi River in Okija

Road works in Nnewi North LGA, Anambra South, delivered by Ferotex Const. Co., supervised by the Ministry of Works.

Project codeANSG/MOW/PRJ/2026/036
StatusUnder construction
Measured progress90% (measured 11 Oct 2026)
LocationNnewi/Ozubulu/Okija, Nnewi North LGA, Anambra South
ContractorFerotex Const. Co.
Supervising ministryMinistry of Works, PD/S
Contract sumNot published
Commencement30 Oct 2024
Planned completion1 May 2026

Timeline

Contract awardCompleted · planned 30 Oct 2024 · actual 30 Oct 2024
Works commenceCompleted · planned 30 Oct 2024 · actual 30 Oct 2024
Works 90% completeIn Progress · actual 11 Oct 2026
Practical completionUpcoming · planned 1 May 2026
Defects period endsUpcoming

Source: Anambra State Ministry of Works project records, as published on Road Tracker. https://roads.anambrastate.gov.ng/p/construction-of-16-51km-lot2-nnewi-to-ozubulu-to-981d0f78

Back to the project