Project factsheet · generated 16 Oct 2026
Construction & Dualization of Nwagu - Nnobi - Nnewi Road
Road works in Anaocha LGA, Anambra Central, delivered by Lebtech Const. LTD, supervised by the Ministry of Works.
| Project code | ANSG/MOW/PRJ/2026/017 |
|---|---|
| Status | Under construction |
| Measured progress | 96% (measured 11 Oct 2026) |
| Location | Agulu,nnobi, Nnewi, Anaocha LGA, Anambra Central |
| Contractor | Lebtech Const. LTD |
| Supervising ministry | Ministry of Works, Highways |
| Contract sum | Not published |
| Commencement | 30 Oct 2024 |
| Planned completion | 30 Oct 2025 |
Timeline
| Contract award | Completed · planned 30 Oct 2024 · actual 30 Oct 2024 |
|---|---|
| Works commence | Completed · planned 30 Oct 2024 · actual 30 Oct 2024 |
| Works 96% complete | In Progress · actual 11 Oct 2026 |
| Practical completion | Upcoming · planned 30 Oct 2025 |
| Defects period ends | Upcoming |
Source: Anambra State Ministry of Works project records, as published on Road Tracker. https://roads.anambrastate.gov.ng/p/construction-dualization-of-nwagu-nnobi-nnewi-road-08edbbd3