Project codeANSG/MOW/PRJ/2026/016
StatusUnder construction
Measured progress33.0% (measured 11 Oct 2026)
LocationEkwulobia,oko,amaokpal, Ufuma, Aguata LGA, Anambra South
ContractorLebtech Const. LTD
Supervising ministryMinistry of Works, Highways
Contract sumNot published
Commencement27 Oct 2025
Planned completion28 Apr 2027

Timeline

Contract awardCompleted · planned 27 Oct 2025 · actual 27 Oct 2025
Works commenceCompleted · planned 27 Oct 2025 · actual 27 Oct 2025
Works 33% completeIn Progress · actual 11 Oct 2026
Practical completionUpcoming · planned 28 Apr 2027
Defects period endsUpcoming