Project factsheet · generated 16 Oct 2026
Construction and Dualization of the Aerotropolis Road 1 and Airport Main Access Road
Road works in Orumba North LGA, Anambra South, delivered by IDC Construction NIG. LTD, supervised by the Ministry of Works.
| Project code | ANSG/MOW/PRJ/2026/030 |
|---|---|
| Status | Under construction |
| Measured progress | 0.5% (measured 11 Oct 2026) |
| Location | Ndikelionwu, Orumba North LGA, Anambra South |
| Contractor | IDC Construction NIG. LTD |
| Supervising ministry | Ministry of Works, Highways |
| Contract sum | Not published |
| Commencement | 21 Aug 2026 |
| Planned completion | 21 Nov 2027 |
Timeline
| Contract award | Completed · planned 21 Aug 2026 · actual 21 Aug 2026 |
|---|---|
| Works commence | Completed · planned 21 Aug 2026 · actual 21 Aug 2026 |
| Works 1% complete | In Progress · actual 11 Oct 2026 |
| Practical completion | Upcoming · planned 21 Nov 2027 |
| Defects period ends | Upcoming |
Source: Anambra State Ministry of Works project records, as published on Road Tracker. https://roads.anambrastate.gov.ng/p/construction-and-dualization-of-the-aerotropolis-road-1-and-b7b97fe9