Project factsheet · generated 16 Oct 2026
Construction and Dualization of the 7.04km Road from the Coca Cola Junction Along the Ziks Avenue Awka to Isiagu (LOT 3 of the Access Road to the Anambra Aerotropolis
Road works in Awka South LGA, Anambra Central, delivered by Ag-vision Const. NIG. LTD, supervised by the Ministry of Works.
| Project code | ANSG/MOW/PRJ/2026/032 |
|---|---|
| Status | Under construction |
| Measured progress | 0% (measured 11 Oct 2026) |
| Location | Awka-Isiagu, Awka South LGA, Anambra Central |
| Contractor | Ag-vision Const. NIG. LTD |
| Supervising ministry | Ministry of Works, Highways |
| Contract sum | Not published |
| Commencement | 24 Sept 2026 |
| Planned completion | 25 Jul 2027 |
Timeline
| Contract award | Completed · planned 24 Sept 2026 · actual 24 Sept 2026 |
|---|---|
| Works commence | Completed · planned 24 Sept 2026 · actual 24 Sept 2026 |
| Works 0% complete | In Progress · actual 11 Oct 2026 |
| Practical completion | Upcoming · planned 25 Jul 2027 |
| Defects period ends | Upcoming |
Source: Anambra State Ministry of Works project records, as published on Road Tracker. https://roads.anambrastate.gov.ng/p/construction-and-dualization-of-the-7-04km-road-from-97cf191a