Project factsheet · generated 16 Oct 2026
Constr. of Solution Modern Gate at the Chukwuemeka Odumegwu Ojukwu University, Uli Campus
Road works in Ihiala LGA, Anambra South, delivered by Anyi Supreme IND. LTD, supervised by the Ministry of Works.
| Project code | ANSG/MOW/PRJ/2026/021 |
|---|---|
| Status | Under construction |
| Measured progress | 90% (measured 11 Oct 2026) |
| Location | Uli, Ihiala LGA, Anambra South |
| Contractor | Anyi Supreme IND. LTD |
| Supervising ministry | Ministry of Works, Highways |
| Contract sum | Not published |
| Commencement | 11 Mar 2025 |
| Planned completion | 10 Jun 2025 |
Timeline
| Contract award | Completed · planned 11 Mar 2025 · actual 11 Mar 2025 |
|---|---|
| Works commence | Completed · planned 11 Mar 2025 · actual 11 Mar 2025 |
| Works 90% complete | In Progress · actual 11 Oct 2026 |
| Practical completion | Upcoming · planned 10 Jun 2025 |
| Defects period ends | Upcoming |
Source: Anambra State Ministry of Works project records, as published on Road Tracker. https://roads.anambrastate.gov.ng/p/constr-of-solution-modern-gate-at-the-chukwuemeka-odumegwu-2074a08b