Project codeANSG/MOW/PRJ/2026/020
StatusUnder construction
Measured progress85% (measured 11 Oct 2026)
LocationUli, Ihiala LGA, Anambra South
ContractorAnyi Supreme IND. LTD
Supervising ministryMinistry of Works, Highways
Contract sumNot published
Commencement18 Jan 2025
Planned completion19 Sept 2025

Timeline

Contract awardCompleted · planned 18 Jan 2025 · actual 18 Jan 2025
Works commenceCompleted · planned 18 Jan 2025 · actual 18 Jan 2025
Works 85% completeIn Progress · actual 11 Oct 2026
Practical completionUpcoming · planned 19 Sept 2025
Defects period endsUpcoming